Before the Wind Creek Hotel and Casino came to Atmore, Alabama, the Poarch Band of Creek Indians managed a wastewater system for roughly 500 residents. The Poarch Creek Indians anticipated that its casino, with 1,600 gaming machines and 236 hotel rooms, would bring an immediate influx of visitors. And that called for the quick construction of a new wastewater treatment facility. Thompson Engineering provided the permitting, design, bidding, awarding and construction of a new 0.5 million gallons per day (MGD) sequencing batch reactor facility in just 18 months.  Highlights of the project include:

The plant was constructed on time and within budget.  It is running at approximately 40% capacity and it produces much cleaner effluent than its permitted limits.